Bond Project - August 16, 2024 Update
Current Activities & Tasks
- CES - Punch List / Touch-Ups
- CHS - Window replacement (continued)
- CES - Boiler installation - Complete
- CES - Parking Lot Prep
- CES - Gym Expansion Block
Upcoming Activities & Tasks
- CES - Block Walls at Gym
- CES - Asphalt Paving at Parking Lot
- CHS - Window Installation Continued