Bond Project - August 16, 2024 Update

CES - Front Entrance with Backlit Logos/Letters
CES - Front Entrance with Backlit Logos/Letters
CES - Media Center - Move-In
CES - Media Center - Move-In
CES/CHS - Parking Lot - Ready for Asphalt
CES/CHS - Parking Lot - Ready for Asphalt
CES - Playground Installation - In Progress
CES - Playground Installation - In Progress

Current Activities & Tasks

  • CES - Punch List / Touch-Ups
  • CHS - Window replacement (continued)
  • CES - Boiler installation - Complete
  • CES - Parking Lot Prep
  • CES - Gym Expansion Block

Upcoming Activities & Tasks

  • CES - Block Walls at Gym
  • CES - Asphalt Paving at Parking Lot