October Updates
Bond Project - October 11, 2024 Update
Current Activities & Tasks
- CHS – Monument Sign Complete.
- CES – Gymnasium Expansion, Roof in Progress.
- ECC – Continue Demolition.
- Schalm – Demolition In Progress
Upcoming Activities & Tasks
- CES – Structural Steel at CES Gym Expansion is complete, roof is in progress.
- ECC – Demolition Continues & Demoing Exterior walls office secured entry.
- ECC – Continue installing new Electrical, Plumbing, & HVAC overhead and in wall
ECC – Early Child Center
CHS – Clawson High School
CMS – Clawson Middle School
CES – Clawson Elementary School