Bond Project - March 21, 2025 Update

ECC - Corridor Floor, Base & Markerboards In Progress
ECC - Corridor Floor, Base & Markerboards In Progress
ECC - Egress (Exit Signs) In Progress
ECC - Egress (Exit Signs) In Progress
ECC - Classroom Sink Fixtures & Markerboards In Progress
ECC - Classroom Sink Fixtures & Markerboards In Progress
ECC - Media Center Casework In Progress
ECC - Media Center Casework In Progress

Current Activities & Tasks

  • ECC – Continue Overhead Mechanical / Electrical.
  • ECC – Cafeteria Clouds Lighting & Mechanical in progress.
  • ECC – Casework Install in progress.
  • ECC – Floor Prep & Floor Install in progress.
  • ECC – Interior Ceiling Grid & Lighting in rooms & corridors in progress.
  • ECC – Corridor Exist Signs install in progress.

Upcoming Activities & Tasks

  • ECC – Continue Classroom Floor Install. 
  • ECC – Ceiling Grid Continues.
  • ECC – Casework Install Continues.
  • ECC – Entry Doors & Hardware Installation Begins. 