Bond Project - December 20, 2024 Update
Current Activities & Tasks
- ECC – Continue Overhead Mechanical /Electrical.
- ECC – Masonry Walls in progress.
- ECC – Ceiling Grid in progress.
- ECC – Painting in progress.
- ECC – VUV Installation in progress.
- ECC – Interior Ceiling Grid & Lighting in rooms & corridors in progress.
- ECC – Hard Tile In Progress
Upcoming Activities & Tasks
- ECC – Continue Mechanical / Electrical Installation.
- ECC – Masonry Wall Continues.
- ECC – Ceiling Grid Continues.
- ECC – Painting Continues.
ECC – Early Child Center
CHS – Clawson High School
CMS – Clawson Middle School
CES – Clawson Elementary School