February Updates

Bond Project - February 21, 2025 Update

ECC - New Exterior Doors Install In Progress
ECC - New Exterior Doors Install In Progress
ECC - Media Center Painting in Progress
ECC - Media Center Painting in Progress
ECC - Water Fountain Install In Progress
ECC - Water Fountain Install In Progress
ECC - Cafeteria Clouds Lighting In Progress
ECC - Cafeteria Clouds Lighting In Progress

Current Activities & Tasks

  • ECC – Continue Overhead Mechanical /Electrical.
  • ECC – Cafeteria Clouds Lighting & Mechanical in progress.
  • ECC – Painting in progress.
  • ECC – VUV Installation in progress.
  • ECC – Interior Ceiling Grid & Lighting in rooms & corridors in progress.
  • ECC – New Exterior Doors install in progress.

Upcoming Activities & Tasks

  • ECC – Casework arrives 2/26 & 2/27.
  • ECC – Cafeteria Clouds Lighting & Mechanical Install Continues.
  • ECC – Ceiling Grid Continues.

ECC – Early Child Center

CHS – Clawson High School 

CMS – Clawson Middle School 

CES – Clawson Elementary School