January Updates

Bond Project - January 31, 2025 Update

ECC - Gymnasium Paint In Progress
ECC - Gymnasium Paint In Progress
ECC - North Side Exterior Lentils In Progress
ECC - North Side Exterior Lentils In Progress
ECC - Main Office Space In Progress
ECC - Main Office Space In Progress
ECC - Corridor Painting In Progress
ECC - Corridor Painting In Progress

Current Activities & Tasks

  • ECC – Continue Overhead Mechanical /Electrical.
  • ECC – North Side Exterior Lentils in progress.
  • ECC – Ceiling Grid in progress.
  • ECC – Painting in progress.
  • ECC – VUV Installation in progress.
  • ECC – Interior Ceiling Grid & Lighting in rooms & corridors in progress.

Upcoming Activities & Tasks

  • ECC – Continue Mechanical / Electrical Installation.
  • ECC – Cafeteria Clouds Install Begins on Monday, February 3rd.
  • ECC – Masonry Wall Continues.
  • ECC – Ceiling Grid Continues.
  • ECC – Painting Continues.