November Updates

Bond Project - November 15, 2024 Update

CES - Gym Addition Wood Finishing Near Complete
CES - Gym Addition Wood Finishing Near Complete
ECC - Library MEP In Progress
ECC - Library MEP In Progress
ECC - Big Chimney Demo & Window Install In Progress
ECC - Big Chimney Demo & Window Install In Progress
ECC - Area D Painting In Progress
ECC - Area D Painting In Progress

Current Activities & Tasks

    • CES - Gym Equipment Divider Curtain Motor & Structure in place, pending wood floor completion for install.
    • CES - Gym Painting Complete.
    • CES - New Gym Wood Finishing near complete.
    • ECC - Demolition near complete.
    • ECC - Continue Overhead Mechanical /Electrical.
    • Schalm - Continue Backfill foundations / tunnels, Site Balancing.

Upcoming Activities & Tasks

    • ECC - Continue Mechanical / Electrical Installation.
    • Schalm - Balancing & Restoration Continue.
    • ECC - Masonry Wall

ECC – Early Child Center

CHS – Clawson High School 

CMS – Clawson Middle School 

CES – Clawson Elementary School