June 20, 2024

6/14/2024

Clawson Public Schools 2021 & 2023 Bond Project CES - Parking Lot Demolition CES - corridor flooring installation CES - corridor flooring installation CES - exterior metal panels installation  Current Activities & Tasks • CES - Metal Panels installation at  Main Entrance addition  • CES - flooring installation at  corridors  • CES - Parking Lot Demolition • CES - Boiler Installation Upcoming Activities & Tasks  • CES - Structural steel  installation at Gym Expansion • CES - Installing doors and  hardware • CES - Storefront doors  installation at Main Entrance  CES - Elementary School CHS – High School June 14, 202