Bond Project - October 18, 2024 Update
Current Activities & Tasks
- CES – Gym Roof – Complete
- CES – Gym Painting – In Progress
- ECC – Continue Demolition
- ECC – Overhead Mechanical / Electrical
- Schalm – Backfill foundations / tunnels
Upcoming Activities & Tasks
- CES – K13 Acoustical Spray
- CES – K-Playground Install
- ECC – Continued Mechanical /Electrical Installation
- ECC – Continued Window Installation
- Schalm – Backfill Continued
ECC – Early Child Center
CHS – Clawson High School
CMS – Clawson Middle School
CES – Clawson Elementary School