October Updates

Bond Project - October 4, 2024 Update

ECC - Continued Demolition & Cleaning
ECC - Continued Demolition & Cleaning
CES - Gym Addition
CES - Gym Addition
Clawson Schools - Monument Sign In Progress
Clawson Schools - Monument Sign In Progress
ECC - Cafeteria
ECC - Cafeteria

Current Activities & Tasks

  • CHS - Monument Sign Near Completion
  • CES - Gymnasium Expansion, Structural Steel on the roof
  • ECC - Continue Demolition
  • Schalm - Demolition In Progress

Upcoming Activities & Tasks

  • CES - Continue Structural Steel at CES Gym Expansion
  • ECC - Demolition Continues
  • ECC - New Electrical, Plumbing, & HVAC will begin install

ECC – Early Child Center

CHS – Clawson High School 

CMS – Clawson Middle School 

CES – Clawson Elementary School