Bond Project - November 1, 2024 Update
Current Activities & Tasks
- CES - Gym Equipment & Scoreboard Installation.
- CES - Gym Painting Continue.
- ECC - Continue Demolition.
- ECC - Continue Overhead Mechanical /Electrical.
- Schalm - Continue Backfill foundations / tunnels, Site Balancing.
Upcoming Activities & Tasks
- ECC - Continue Mechanical / Electrical Installation.
- Schalm - Balancing & Restoration Continue.
- CES - Gym Wood Floor Installation.
ECC – Early Child Center
CHS – Clawson High School
CMS – Clawson Middle School
CES – Clawson Elementary School